Home / Deployment scenarios / Three data centres into one
Reference deployment Data centre consolidation

Three ageing data centres, one modern home

A manufacturing group grew by buying companies, and with each one it inherited a server room. Ten years on, it runs three data centres with three hypervisors, seven storage arrays and three directories, and pays to cool all of them. This design brings everything into one primary site and one recovery site, wave by wave, without stopping a single production line.

SectorManufacturing
Estate~900 VMs, 120 physical
Programme11 months, 6 waves
ModelPrimary DC + DR site
The situation

Three of everything, and none of it young

The group makes industrial components at 24 plants. Its IT runs from three sites: a server room at head office on VMware, a plant-campus data centre on Hyper-V that came with the first acquisition, and a smaller room at the second acquired unit with a mix of an older KVM stack and about 35 physical servers. Together they host about 900 virtual machines and 120 physical servers.

Most of the hardware is between six and eleven years old. Two of the storage arrays are past vendor support, the plant-campus site has had two cooling failures in eighteen months, and the head-office room cannot take more power. Each site has its own firewall rules, its own backup tool and its own Active Directory domain, and nobody has a complete list of what depends on what.

The board approved a refresh, but refreshing three sites would mean buying three of everything again. The CIO’s question was whether the group could end up with one well-run primary site and a proper recovery site, for less than a like-for-like refresh, and move without disrupting plants that run around the clock.

What could not be compromised

  • Plants run three shifts, seven days a week. ERP, MES interfaces and dispatch systems cannot be down for more than a planned four-hour window, once a month.
  • Applications that talk to each other must move together, or their traffic must be proven to cope with the distance during the move.
  • About 20 systems are tied to physical hardware: licence dongles, per-socket licences or vendor certification.
  • The IT team is 14 people across three sites, used to different tools. The end state must be something one team can run.
  • Year-end close and the annual plant maintenance shutdown are fixed. Migration waves fit around them.
Options weighed

Four ways to fix three ageing sites

Each option was costed over seven years, including hardware, facilities, power, people and migration effort.

OptionWhat worksWhat does notVerdict
Refresh all three sites in placeNo migration, familiar layout.Three sets of hardware, cooling, security and backup. The head-office room still cannot take more power.Rejected
Move everything to public cloudNo hardware to own.Plant interfaces need low latency and the steady load is high. Seven-year cost was the highest of the four.Rejected
Rebuild head office as the primaryOwned site, no colocation fees.Needs new power feed, cooling and fire suppression, about 14 months of civil work before any migration.Rejected
Primary in Tier III colocation, DR in a second colocationFacility risk handed to a specialist, power and cooling at modern efficiency, migration can start within four months.Monthly colocation fees. WAN to the plants must be redesigned for one hub.Chosen
Target architecture

One primary site, one recovery site, one way of running both

The primary site runs one virtualisation platform, one storage platform and one network fabric, with a small bare-metal pool for systems that must stay physical. The recovery site receives storage replicas and a second backup copy, and holds warm compute that takes over in a disaster. The three old sites drain into the new one in dependency waves.

Scroll sideways to see the whole diagram →
LEGACY DC A: HEAD OFFICELEGACY DC B: PLANT CAMPUSLEGACY DC C: ACQUIRED UNITMIGRATION FACTORYNEW PRIMARY DC, TIER III COLOCATIONDR SITEVMware estate420 VMs, 45 physical serversMOVINGHyper-V estate310 VMs, 40 physical serversMOVINGMixed estate170 VMs, 35 physical serversMOVINGDiscovery and replicationdependency map, wave toolingWAN and SD-WAN hub24 plants, offices, 2 ISPsEdge firewallsone policy, active-standbySpine-leaf fabric2 x 100G spines, 25G to every hostVirtualisation cluster16 hosts, one hypervisorNEWBare-metal pool14 servers, licence-bound appsBackupimmutable, 35 daysAll-flash storage~110 TB usable, 2:1 reductionOne directorymerged from 3 domainsMonitoring and CMDBone view of every systemPower and coolingabout 150 kW IT load, PUE ~1.5, 12 racksSecond WAN hubplants dual-homedDR compute8 hosts, warmStorage replicaasync, 15 minBackup copysecond, offline1wavesagents234Data / replicationControl / API callUser or API trafficScheduled copy
Numbered flows: (1) workloads replicate from the three legacy sites into the new cluster, one dependency wave at a time, (2) plants and offices reach the primary site through the SD-WAN hub and one firewall policy, (3) storage replicates to the recovery site every 15 minutes, (4) backups are copied to the recovery site and kept offline.
Building blockWhy it is there
1 WAN and SD-WAN hubEvery plant and office connects to the primary site over two paths, a leased line and broadband, with the recovery site as a second hub. Replaces three separate WAN designs.
2 Edge firewallsOne active-standby pair with one rule set, rebuilt from the three old rule bases. About 60% of the old rules were unused or duplicated and are not carried over.
3 Spine-leaf fabricTwo 100G spines and 25G to every host. Storage, VM and management traffic on separate networks, designed so a link or switch failure does not stop anything.
4 Virtualisation clusterSixteen hosts on one hypervisor replace three platforms. VMs are converted during migration, so the team learns one tool and one set of runbooks.
5 Bare-metal poolFourteen current servers for the roughly 20 systems that must stay physical, combined where licences allow. Each one documented with why it cannot be virtualised.
6 All-flash storageOne array with deduplication and compression replaces seven. Snapshots feed backup and asynchronous replication feeds the recovery site.
7 One directoryThe three Active Directory domains are merged into one, with group policies cleaned up. Done early, because almost every migration depends on it.
8 Recovery siteStorage replica, warm compute for the critical tier and a second, offline backup copy. Failover is tested twice a year with real applications.
Sizing, worked out

Sized from what the estate actually uses

Ninety days of performance data was collected from all three sites. Most VMs were sized years ago and never revisited, so allocated capacity is far above real use.

ResourceThree sites todayNew primary siteBasis
vCPU~3,600 allocated, ~1,300 in use at p9516 hosts, 2 x 32 cores each, 1,024 coresRight-sized to ~2,700 vCPU at 4:1 = ~675 cores, +30% growth, N+2 hosts
Memory~10.8 TB allocated, ~7 TB in use16 x 1 TB = 16 TB~8.5 TB right-sized, +30% growth, still fits with 2 hosts down
Physical servers12014 bare-metal servers~70 virtualised, ~30 retired, ~20 stay physical on newer hardware
Storage7 arrays, ~420 TB raw, ~210 TB used1 all-flash array, ~110 TB usable~60 TB cold data to archive, 150 TB active +40% growth = 210 TB, at 2:1 reduction
Racks~46 across three rooms12 primary, 6 DRMeasured power per rack, 12 kW design
IT power~310 kW, PUE about 2.0~150 kW primary + ~40 kW DR, PUE about 1.5~620 kW at the meter today, ~285 kW after
WAN3 hub designs1 SD-WAN hub per site, 2 x 1G internet + leased linePlant traffic measured at peak shift change

The power figures use measured draw from the three sites, not nameplate ratings. Colocation contracts are written for 12 racks with an option for 4 more, so growth does not mean a new site.

How it is delivered

Six waves, planned around how applications really talk to each other

Waves are built from observed network traffic between systems, not from the server list. Systems that talk to each other a lot move together. Nothing moves during year-end close or the plant shutdown.

1

Discover and plan

Weeks 1 to 8

Traffic and performance collected from all three sites. Dependency groups built, owners confirmed, licence-bound systems identified. Colocation contracts signed and hardware ordered.

Gate: Every system has an owner, a wave, a move method and a rollback plan.

2

Build the primary site

Weeks 9 to 18

Racks, fabric, firewalls, cluster, storage and backup built from code. Directory merge done. SD-WAN hub live with plants dual-homed to old and new hubs.

Gate: Failure tests passed: host, switch, storage controller and WAN link.

3

Pilot wave

Weeks 19 to 22

About 60 low-risk VMs, including file servers and internal tools, move from all three sites. Tooling and runbooks tuned.

Gate: No incidents for two weeks, measured move time within plan.

4

Production waves 2 to 6

Weeks 23 to 40

Dependency groups move in monthly windows, the largest risk last. ERP and MES interfaces move together in one planned four-hour window.

Gate: Each wave stable for 14 days before the next starts.

5

Build DR and close sites

Weeks 41 to 48

Recovery site live with replicas, first full failover test. Old hardware wiped with certificates, rooms handed back or repurposed.

Gate: Failover test passed, three sites empty, power contracts closed.

Way back: Each VM keeps its source copy powered off at the old site until the wave is signed off, so going back is a power-on and a DNS change. For the ERP wave, the old system stays read-only for 14 days with a tested reverse sync.
Risks, handled up front

What could go wrong in a three-way move

RiskWhat could happenHow the design handles it
Hidden dependenciesA system moves and breaks one nobody knew it talked toWaves built from 90 days of observed traffic, not from documentation. Anything unexplained gets an owner before its wave is scheduled.
Latency between sites mid-moveAn application is split across old and new sites and slows downDependency groups move together. Where that is impossible, the inter-site link is load-tested with the real application first.
Plant disruptionMES or dispatch interfaces fail during a shiftPlant-facing systems move only in agreed four-hour windows, with plant IT on site and a rehearsed rollback.
Old hardware failing before its turnAn out-of-support array fails mid-programmeThe two oldest arrays are in the first production waves, and their backups are copied to the new site in the build phase.
One team, three habitsStaff keep running things the old wayOne runbook set, training from the build phase, and the team does the pilot wave themselves with support alongside.
What was optimised

Where the savings come from

~54%

Lower power draw

From about 620 kW at the meter to about 285 kW across both new sites, through newer servers and better cooling.

46 to 18

Fewer racks

Right-sized hosts and one storage array fit in twelve racks at the primary site and six at DR.

3 to 1

One of everything

One hypervisor, one storage platform, one firewall policy, one directory and one backup tool.

~30

Servers retired

Systems with no users or a modern replacement are switched off, not migrated.

60%

Fewer firewall rules

Unused and duplicate rules from three old rule bases are not carried over.

2:1

Storage reduction

Deduplication and compression on all-flash, with cold data moved to cheaper archive.

Outcomes

What the design is built to deliver

MeasureBeforeDesign target
Facility power at the meter~620 kW~285 kW, saving roughly ₹2.3 to 2.9 crore a year at ₹8 to ₹10 per kWh
Seven-year costLike-for-like refresh of three sites25 to 35% lower, including colocation fees
RecoveryBackups only, restore in daysRPO 15 minutes, RTO 4 hours for critical systems, tested twice a year
Platforms to run3 hypervisors, 7 arrays, 3 domains1 of each
Hardware in supportAbout halfAll, with a five-year support term
Change to an applicationDays of finding where it runsOne CMDB, one monitoring view

Targets are confirmed after discovery. Power savings depend on measured draw, colocation pricing and the final number of systems retired, and are recalculated with your own meter data during assessment.

Skills this draws on

What a team needs to deliver this

Discovery and dependency mapping

Building migration waves from observed traffic and real usage, not from spreadsheets.

Data centre and colocation design

Rack, power, cooling and Tier III colocation selection and contracts.

Network design

Spine-leaf fabrics, SD-WAN hub design and firewall rule rationalisation.

Virtualisation migration

Moving VMs between hypervisors, P2V and conversion at scale with rollback.

Storage consolidation

Moving many arrays onto one platform, replication and tiering cold data.

DR design and testing

Recovery tiers, replication and failover tests that use real applications.

About this page. This is a reference deployment: a worked design built from requirements we see repeatedly in this kind of organisation. It is not a description of a specific client. Figures are design targets and planning estimates; real numbers depend on your workloads and are confirmed during assessment. We are glad to walk through how it would apply to your environment.

Running more data centres than your business needs?

Send us a rough inventory of your sites, hardware ages and power bills. We will come back with a plain first view of what consolidation could look like, what it would cost and where the savings would come from.