What disaster recovery really costs
DR cost comes down to one question: how much of your production setup has to be running at the DR site before a disaster happens? Answer that for each application and most of the budget follows.
Where the money goes
- Space and power at the DR site. Your own second data centre, a colocation rack, or a cloud account.
- Compute that runs every day. Servers kept powered on for databases, directory services and any warm or active tiers.
- Storage. A full copy of protected data, plus snapshots and backup versions. Plan for more than one copy's worth of capacity.
- Network links. Replication bandwidth between sites, ideally from two different providers.
- Software licences. Databases, hypervisors, backup and replication tools. Some vendors charge in full for a standby copy and some do not, so read the contract.
- People and drills. Time to write and maintain runbooks and to run tests at least once or twice a year.
Rough planning ranges
For a first conversation it helps to express DR running cost as a share of what the production infrastructure costs. These are the ranges we use to compare options before detailed sizing.
| Pattern | DR running cost vs production | Why |
|---|---|---|
| Backup & restore | About 10–20% | Mostly storage and backup software. Almost no compute runs at DR. |
| Pilot light | About 20–35% | Replicated storage plus a small set of always-on core servers. |
| Warm standby | About 40–60% | The whole stack runs, at reduced size. |
| Active-passive | About 80–100% | A full-size copy that mostly sits idle. |
| Active-active | 100% or more | Two full sites, plus the cost of changing the application. |
These are planning ranges, not a quote. Use them to compare options early, and replace them with real sizing before a budget is approved.
A worked example
Say production has 40 virtual machines and 30 TB of data. After talking to the business owners, 8 of those VMs are critical (tier 1), 20 are important (tier 2), and 12 can wait a day or two (tier 3).
Option A: protect everything the same way
Build a full active-passive copy. The DR site needs hardware for all 40 VMs, running all the time, plus a full replicated copy of the 30 TB.
Option B: protect by tier
- Tier 1 (8 VMs) on warm standby at about half size.
- Tier 2 (20 VMs) on pilot light: databases running small, application servers off.
- Tier 3 (12 VMs) on backup and restore.
Day to day, Option B runs the equivalent of roughly 7 VMs at the DR site instead of 40. Tier 1 still recovers just as fast as it would under Option A.
There is a catch, and it depends on where the DR site is:
- On-premises or colocation: you still need hardware for tiers 1 and 2 (28 VMs) ready to start, because you cannot buy servers on the day of a disaster. The saving is in power, licences and the tier 3 capacity, not in all the hardware.
- Cloud DR: you pay only for the small always-on footprint and the storage. Full capacity is created on drill day or disaster day. This is where the tiered approach saves the most.
Costs people forget
- Getting data back. After a cloud failover, moving data back to your own data centre can carry large egress charges. Plan failback before you need it.
- The first copy. Seeding tens of terabytes over a WAN link can take weeks. It is often faster to ship encrypted disks for the first copy.
- Drill time. A full failover test takes several people most of a day, plus preparation. Budget for it every year.
- Keeping DR current. Patching DR templates, renewing certificates and updating firewall rules at the DR site is ongoing work.
- Licence clauses. Running a standby database or hypervisor may need its own licence, depending on the vendor and how the standby is used.